UPDATE: The latest on the Basin Avenue project

The Basin Avenue improvement project has been inconveniencing drivers for seven months now and Nye County Public Works Director Tom Bolling assured the community in July that everything would wrap up prior to the Fall Festival. Although this was the original expectation, the completion date has once again shifted and the project will only be partially finished before the largest public event of the year in Pahrump.

The paving of the bulk of the 1.2-mile stretch of Basin Avenue will not take place until after Fall Festival is said and done. However, the section that directly fronts Petrack Park, where the Fall Festival is held, will see its brand new surface laid in time for the big event. This includes paving of the intersection of Basin Avenue at Dahlia Street, as well, meaning that heavily used intersection will soon be operational once more.

“We (Nye County road crews) are finishing up (excavation and prep work on) the Dahlia intersection through the Whitney intersection. We’re scheduled to start paving Monday (Sept. 11), although we’ll probably push that to Wednesday (Sept. 13),” Bolling reported at the Nye County Commission meeting earlier this week. “But it will be paved next week. And we’re hoping to get it striped two days before the festival, so right under the wire.”

The festival runs Sept. 21-24 at Petrack Park in Pahrump.

Bolling stressed that the paving he was referencing is only from Dahlia Street through the intersection of Basin and Whitney Lane, with the rest of the mainline, from Whitney Lane west to Blagg Road, to remain as gravel. He said it’s his department’s plan to have the last of the paving and striping done immediately following the Fall Festival.

The road project kicked off in February and was originally scheduled to finish in mid-May. The process of bidding and awarding the contracts for the paving caused delays.

Nye County Public Works in charge of handling all of the excavation and backfill, along with any other necessary preparatory work. Contractors are being used for the paving and concrete associated with the project. Most of the contract work has been awarded to Las Vegas Paving Corp., which undertook the paving at the Basin Avenue and Blagg Road intersection and will also do the Dahlia intersection and Basin mainline paving. Pahrump-based Performance Concrete LLC was selected for the concrete work.

Motorists are asked to use caution and exercise patience whenever traveling through construction and are reminded that traffic fines are doubled in all work zones.

Contact reporter Robin Hebrock at rhebrock@pvtimes.com

Don't miss the big stories. Like us on Facebook.
THE LATEST
RAM event: Free medical clinic needs your help

Next weekend, Remote Area Medical will be bringing its pop-clinic to the valley for the eighth straight year and members of the local host group committee are urging the public to get involved by donating their time to this life-changing event.

USO Benefit Show set to be the best yet — here’s how to get a ticket

The Nevada Silver Tappers are well-known for their patriotic routines and their generosity to the veteran community and this October, these elements will combine into two nights of fantastic fundraising with the annual USO Benefit Show.

How a Soroptomist scholarship helped a Pahrump mom of 3

Embarking on an educational path as an adult can be challenging and for those acting as head-of-household, it can be all the more difficult.

A Smoky Valley curtain call: Youth theater debuts a Disney classic

Andrew Sweeney played multiple roles as the prince, the beast, Monsieur D’Arque and the baker. “My favorite part of BATB JR was getting to be part of the team and meeting all the other cast members,” he said. “I didn’t feel nervous because we were very prepared for the performance.”

Peek inside this senior-living community’s gardens (GALLERY)

Spring Mountain Apartments, a low-income senior living community in Pahrump, has a brand new community garden to enjoy thanks to a partnership with two of the valley’s major nonprofit organizations, the NyE Communities Coalition and the Master Gardeners with the University of Nevada, Reno Cooperative Extension.

1,000-plus cats and dogs spayed/neutered

In just seven months’ time, Tails of Nye County has managed to spay or neuter over 1,000 stray cats and personal pets in the Pahrump area with the help of funding from the Nye County American Rescue Plan Act Grant Program.

Want to seek public office? 2 seats up for appointment on Beatty Town Advisory Board

The deadline is 5 p.m. Oct. 30 to submit letters of interest to fill two seats on the Beatty Town Advisory Board that are up for reappointment after the end of the year. Letters of interest can be submitted to the Beatty Town Office. What you need to know.

Lakeview Golf Course on the upswing

Lakeview Executive Golf Course will remain under the operation of CourseCo for another five years, following renewal of a management contract with the town of Pahrump. Here’s how the troubled course turned itself around.