61°F
weather icon Mostly Clear

UPDATE: Basin Avenue roadwork won’t be finished until September — here’s why

What started in February as a projected four-month project is still underway and area motorists will see no relief from the construction on Basin Avenue in the coming weeks. Despite two paving contracts being awarded earlier this month, the county is anticipating that the Basin Avenue rebuild will not wrap up until sometime in September.

“Currently, public works is working on the subgrade and Type II for phase 4 Dahlia intersection concrete. While we have that area excavated, we plan on doing the subgrade rebuild for phase 3 Dahlia intersection,” Nye County Public Works Director Tom Bolling told the Pahrump Valley Times on July 11. “We still have roughly 1,200 linear feet of phase 2 Basin mainline to excavate and backfill and we will finish that after the Dahlia intersection is complete.”

While the excavation is in process, the Dahlia Street intersection is closed to traffic.

“We are planning all this work to be competed by the end of August,” Bolling continued. “Then we will import Type II and Finish grade for paving. Since Las Vegas Paving was awarded the contracts for both phase 2 and phase 3 paving, we will schedule them to pave both phases at the same time, more than likely around the middle of September.”

What is by far the largest community event in the valley each year, Fall Festival, is scheduled for the end of September and with thousands of attendees expected, Bolling said the goal is to see the Basin Avenue project finished before the festival takes place.

“We, of course, will be complete by the time the Fall Festival gets here,” Bolling stated, adding, “We are going to push for completion earlier than what I’ve discussed with you, but there are a lot of facets that go into finishing the road.”

The 1.2-mile Basin Avenue project kicked off in January with Nye County crews handling all of the preparatory work needed prior to the install of all new asphalt, such as excavation and backfill of the roadway and included intersections at Blagg Road and Dahlia Street. The original estimate was a completion by the close of May but delays cropped up when the county received no bids on the first paving contract. The county was eventually able to secure Las Vegas Paving Corp. for the Basin and Blagg intersection paving but the delay resulted in the overall completion date being pushed back.

Now, the Basin and Blagg intersection is finally paved and the county is all set to go with its paving contracts for the main stretch of Basin from Blagg to Highway 160 as well as the Dahlia intersection, both of which also went to Las Vegas Paving. The Basin Phase 2 Mainline contract comes with a $607,000 price tag while the Basin Phase 3 Dahlia Intersection will run the county $289,000. As Bolling noted, paving is expected to begin in September.

Contact reporter Robin Hebrock at rhebrock@pvtimes.com

Don't miss the big stories. Like us on Facebook.
THE LATEST
RAM event: Free medical clinic needs your help

Next weekend, Remote Area Medical will be bringing its pop-clinic to the valley for the eighth straight year and members of the local host group committee are urging the public to get involved by donating their time to this life-changing event.

USO Benefit Show set to be the best yet — here’s how to get a ticket

The Nevada Silver Tappers are well-known for their patriotic routines and their generosity to the veteran community and this October, these elements will combine into two nights of fantastic fundraising with the annual USO Benefit Show.

How a Soroptomist scholarship helped a Pahrump mom of 3

Embarking on an educational path as an adult can be challenging and for those acting as head-of-household, it can be all the more difficult.

A Smoky Valley curtain call: Youth theater debuts a Disney classic

Andrew Sweeney played multiple roles as the prince, the beast, Monsieur D’Arque and the baker. “My favorite part of BATB JR was getting to be part of the team and meeting all the other cast members,” he said. “I didn’t feel nervous because we were very prepared for the performance.”

Peek inside this senior-living community’s gardens (GALLERY)

Spring Mountain Apartments, a low-income senior living community in Pahrump, has a brand new community garden to enjoy thanks to a partnership with two of the valley’s major nonprofit organizations, the NyE Communities Coalition and the Master Gardeners with the University of Nevada, Reno Cooperative Extension.

1,000-plus cats and dogs spayed/neutered

In just seven months’ time, Tails of Nye County has managed to spay or neuter over 1,000 stray cats and personal pets in the Pahrump area with the help of funding from the Nye County American Rescue Plan Act Grant Program.

Want to seek public office? 2 seats up for appointment on Beatty Town Advisory Board

The deadline is 5 p.m. Oct. 30 to submit letters of interest to fill two seats on the Beatty Town Advisory Board that are up for reappointment after the end of the year. Letters of interest can be submitted to the Beatty Town Office. What you need to know.

Lakeview Golf Course on the upswing

Lakeview Executive Golf Course will remain under the operation of CourseCo for another five years, following renewal of a management contract with the town of Pahrump. Here’s how the troubled course turned itself around.